Runway reseal


We are moving forward on the runway sealcoating/repainting project.  The runway will need to be closed for 2-3 days depending on weather.  We have requested the work be done Monday - Wednesday as these are days we typically see the least flying activity.  The dates we have proposed to the contractor are:
June 18 - 20, 2012 or June 25 - 27, 2012
The first activity you will notice is the contractor cleaning and filling all cracks on the runway.  Following that the sealcoat will be applied and allowed to dry for at least 24 hours before the runway numbers and markings are repainted.  This process is much the same as we did two years ago on the roadways and taxiways.
Your help and cooperation with this will be appreciated.  If you have any concerns, or conflicts with these dates, please let me know immediately.
 Jeff